Onward. And upward. The Mary Free Bed Rehabilitation Hospital Construction Blog Our new facility has 6 stories.  Our history has thousands.
26Nov 2013

Concrete Precast Arrives on Site

The precast for the new Mary Free Bed building is set to arrive tomorrow. Since the hospital is located in a city environment, there’s no extra room to store the panels on our site until the construction workers are ready to hang them on the building.

Kerkstra Precast, located in Grandville, Mich, is producing our concrete precast panels that will transform our new building from a steel structure into an enclosed building.

Concrete precast fun facts:

  • Some of the panels are up to 40 feet long
  • The approximate panel count is 515 panels, which amounts to 74,778 square feet/1,606.41 cubic yards
  • The heaviest piece is around 46,100 lbs.
08Jan 2014

Construction Timelapse Part 5 (12.19.13 - 1.7.14)

View the latest progress from our construction project.

31Dec 2013

Construction Time Lapse - Part 4

View the latest progress of Mary Free Bed Rehabilitation Hospital's expansion project.

23Dec 2013

Mary Free Bed Crowning Ceremony

Mary Free Bed marked a major milestone in its $62.5 million expansion project on December 19, 2013. A Scandinavian tradition, the Crowning Ceremony includes placing an evergreen tree on the structure to symbolize growth and bring good luck. View more photos of the historic event >

Mary Free Bed Crowning Ceremony