Onward. And upward. The Mary Free Bed Rehabilitation Hospital Construction Blog Our new facility has 6 stories.  Our history has thousands.
27Sep 2013

Floor Order Update

The construction team at Mary Free Bed is now planning to fit out the new 5th floor of the addition, which will now include the skilled nursing facility so program floors can be closer together.

The new floor order is the following:

1st floor:  Mary Free Bed parking and O&P Clinic
2nd floor: Mercy Health Saint Mary's parking
3rd floor:  Spinal Cord Injury Program and general therapy patients
4th floor:  Brain Injury & Stroke programs
5th floor:  Skilled nursing facility
6th floor:  Shelled space

20Sep 2013

New Aerial Photos of Mary Free Bed’s Construction Site

Enjoy these aerial photos of the Mary Free Bed construction site taken on August 24, 2013. Visit recent images to view more.

aerial photo of Mary Free Bed construction site

Photos courtesy of John Wagner.

12Sep 2013

First piece of steel is set

We currently have 15 trailers full of steel that are being installed. Our first piece of steel was placed on September 10.

Fun fact: the first third of the new Mary Free Bed building is 500 tons, which is equal to one 747 jetliner or 250 average weight (4,000 lbs) cars.

Mary Free Bed Construction Project

 3 4 5 6 7 8 9 10 11 12 